Wednesday, April 20, 2011

Stone said that the interim plan would still involve removing 2,500 truckloads of sediment from the southern end of the watershed, where there is little vegetation. Right now, the plan is for trucks to travel along Oak Grove Dr. to Berkshire and on the freeway. The sediment would be dumped in the Scholl Canyon Landfill near Glendale.

In response to a question from councilman Phil Barela, Stone said that they do not plan to run the trucks during the drop off and pickup times at nearby La Canada High School.

Hahaslide1 The first step in the interim plan would be restoring the access road to the outside, followed by removing the sediment.  The plan would not start until the area dries significantly, Stone said — although they emptied the reservoir last week, discharging the flow into the Arroyo Seco, the ground is still too wet to work on.

The interim plan also involves modifying the drainage areas, including higher and finer-grain “trashracks” that block solid matter from entering the dam spillways.

Stone said there would also be public hearings announced before the interim plan begins to sound out public comment, including which surface streets would be actually used by the trucks.

Pictured: the interim plan involves removing 25,000 cubic yards
of sediment from the Devil’s Gate Dam to an area 100 feet upstream.

 

TrackBack

TrackBack URL for this entry:
http://www.typepad.com/services/trackback/6a00d83455629c69e2014e6115bb57970c

Listed below are links to weblogs that reference Public Works details Hahamongna interim plan:

Comments